Farm Grid Connection Explained
Quick answer
What does my farm grid connection mean for a battery?
Your grid connection is the supply link between your farm and the local network, run by Scottish Power Energy Networks or SSEN. Before a battery is connected, the network operator must be notified, and larger systems need approval under G99. Your installer handles the paperwork, so you rarely need to contact the DNO yourself.

What are the key facts?
- Your DNO must be notified before or after a battery is connected
- G98 covers smaller systems (notify after); G99 covers larger ones (approve before)
- Scotland has two DNOs: SPEN (central and south) and SSEN (north)
- Battery storage counts towards G98/G99 thresholds alongside solar
- Your installer handles all DNO paperwork and applications
- Some batteries can export to the grid, depending on inverter and tariff
Last updated: 11 November 2026
Your farm grid connection is the link between your property and the electricity distribution network. Understanding how it works is important when considering battery storage, as it affects what you can install and what approvals are needed. This guide explains the key concepts for Scottish farmers.
What is a farm grid connection?
Your grid connection is the physical and contractual link between your farm and the electricity distribution network. It determines how much power you can import from the grid and, if you have solar or battery storage, how much you can export back. The connection is managed by your regional Distribution Network Operator (DNO).
What is the difference between G98 and G99?
G98 covers smaller, single-phase or low-output inverter systems that can be connected first and notified to the DNO shortly afterwards. G99 covers larger or three-phase systems, which must be approved before they are switched on. Battery storage counts towards these limits alongside any solar inverter, so adding a battery to an existing array can move a farm from one process to the other. Your installer works out which applies once the inverter sizes are known.
Who is my DNO in Scotland?
Scotland has two DNOs:
- Scottish Power Energy Networks (SPEN): Covers central and southern Scotland, including Glasgow, Edinburgh, Ayrshire, Lanarkshire, and the Borders.
- Scottish and Southern Electricity Networks (SSEN): Covers northern Scotland, including the Highlands, Aberdeenshire, Tayside, Fife, and Argyll.
We confirm your DNO during the survey and handle all necessary communications on your behalf.
Do I need DNO approval before installing a battery?
Yes. When you install battery storage, you must notify your DNO. For smaller systems, this is a simple notification after installation. For larger systems or those that can export to the grid, prior approval is required before installation can begin.
What is the G99 application process?
A G99 application is the formal process for connecting generation or storage equipment above a certain threshold to the grid. The DNO reviews the application to ensure the local network can accommodate the additional equipment. We prepare and submit the application on your behalf, and installation proceeds once approval is received. The process typically takes several weeks, depending on the DNO and the complexity of the application.
Can a battery system export power to the grid?
Some battery systems can export stored energy back to the grid, but this depends on your inverter capabilities, your DNO agreement, and your electricity tariff. Exporting can be beneficial if you are on an export tariff, but it is not always the most economical use of stored energy. We discuss export options during your survey if this is something you are interested in.
Will a battery affect my farm electricity tariff?
A battery changes when you draw power from the grid, which can affect which tariff is best for you. If you are on a time-of-use tariff, you can charge the battery during off-peak periods and discharge during peak times to reduce costs. We discuss tariff implications during the survey and can recommend whether a tariff change might benefit you.
What happens during the grid connection process?
We handle the entire process for you. After your survey, we determine whether a notification or full application is needed. If an application is required, we prepare the technical details and submit it to your DNO. Once approved, we schedule the installation. After installation, we confirm compliance and provide you with all relevant documentation.

Frequently asked questions
What is a farm grid connection?
A farm grid connection is the link between your property and the electricity distribution network. It determines how much power you can import and export. Most Scottish farms have either a single-phase or three-phase connection managed by the regional DNO.
Do I need to tell my DNO before installing a battery?
Yes. You must notify your Distribution Network Operator when installing battery storage. For larger systems, prior approval may be required. We handle all notifications and applications as part of the installation process.
Can a battery system export power back to the grid?
Some battery systems can export stored energy to the grid, but this depends on your inverter, tariff and DNO agreement. We discuss export options during your survey if this is something you are interested in.
What is the G99 application process?
A G99 application is required when connecting generation or storage equipment above a certain threshold to the grid. We prepare and submit the application on your behalf, and installation can proceed once DNO approval is received.
Who is my DNO in Scotland?
In Scotland, the DNOs are Scottish Power Energy Networks for central and southern Scotland and Scottish and Southern Electricity Networks for northern Scotland and the Highlands. We confirm your DNO during the survey.
Reviewed by the Scottish Energy Efficiency team.
Last updated: